Comanche Trail HROM

  • Project typeDrainage Improvements
  • Project value$4,000,000
Drainage Improvements

Culvert improvements are proposed for Comanche Trail between Malaga Drive and Marina Drive to address existing hazards from flood waters overtopping this location. In conjunction with the culvert improvements, the road will be widened and elevated to reduce the probability of flood waters flooding the roadway during high intensity rainfall events.

The project is located in District 7.

February 2024 Project Update

Construction of the new arch culvert, retaining walls and pavement have been completed. Traffic railing along the bridge and pavement markings will be installed in the coming weeks. The roadway should be opened to traffic in late January to mid-February.

 

Project meetings

  • Pre-Construction Community Meeting was held at 6pm on Wednesday, October 26, 2022
  • May 26, 2022 Community Meeting
  • March 21, 2021 Community Meeting
  • April 1, 2021 Community Meeting

 

Project news

  • There is no project news available at this time.

 

 

 

 

 

Location

7300 Comanche Trail, Fort Worth 761135  View Map

Google Map