Crowley Road & Altamesa Boulevard Intersection Improvements

  • Project typeStreet & Transportation Improvements
  • Project value$1,000,000
Street & Transportation Improvements

This project will improve intersection performance by constructing an additional left turn lane from northbound Crowley Road to westbound Altamesa Boulevard and from eastbound Altamesa Boulevard to northbound Crowley Road. New traffic signals with new signal support structures for this intersection and new accessible sidewalk ramps are also included in the project.

This project is in Council District 8

 

December 2022 Update 

  • Please watch for posted electronic signboard information and use caution through project site

  • McLendon Construction
  • Project concrete work is completed. Traffic lanes open.
  • Mid-January installation of permanent signal poles which are delayed due to supply issues. Watch for adjacent lane closures through area for placement of poles. Single day closure anticipated. 
  • Project estimated completion January 2023

 

Project meetings

  • There are no upcoming meetings at this time.

Project news

  • There is no project news available at this time.

Location

6600 Crowley Road, Fort Worth 76133  View Map

Google Map