Ryan Place, Rosemont and Paschal Area Water and Sewer Improvements
- Project typeWater & Wastewater Improvements
- Project value$4,389,528.00
Existing water and sanitary sewer mains will be replaced in streets and alleys in an area bound by Cantey Street to the north, the railroad to the east, Dickson Street to the south and Waits Avenue to the west.
This project also includes design work - southeast of the TCU area - to replace a 390-foot segment of an existing water main that is close to collapsing. The segment crosses Sycamore Creek, north of East Seminary Drive and east of Carter Park Drive.
The affected streets and alleys include:
University Place, Frisco Heights and Paschal neighborhood associations
- West Cantey Street from Waits Avenue to 8th Avenue (water)
Paschal neighborhood association
- Cleburne Road from West Cantey Street to 180 linear feet south of Lowden Street (water)
Ryan Place and Paschal neighborhood associations
- Cleburne Road from Livingston Avenue to West Cantey (water)
- West Lowden Street from Cleburne Road to 8th Avenue (water)
- Stanley Avenue from Cleburne Road to West Berry Street (water)
Ryan Place, Paschal and Las Familias de Rosemont neighborhood associations
- Livingston Avenue from Cleburne Road to West Biddison Street (water)
Ryan Place and Las Familias de Rosemont
- West Berry Street from Stanley Avenue to James Avenue (water)
Las Familias de Rosemont neighborhood association
- Livingston Avenue from West Biddison Street to Dickson Street (water)
- Shaw Street from the west right-of-way line of Livingston Avenue to the east right-of-way line of Livingstone Avenue (sewer)
Ryan Place Improvement neighborhood association
- 5th Avenue from West Lowden Street to Ryan Place Drive (water)
- 6th Avenue from Bowie Street to Ryan Place Drive (water)
- Alley between 6th Avenue and Willing Avenue from West Berry Street to 870 feet north (sewer)
- Alley south of Ryan Place Drive from Ryan Place Drive to 170 feet south (sewer)
- Willing Avenue from West Bowie Street to West Lowden Street (water)
- Ryan Place Drive from 6th Avenue to 5th Avenue (water);
- West Berry Street from Livingston Avenue to James Avenue (water)
Ryan Place Improvement neighborhood association and Paschal neighborhood association
- Cleburne Road from Livingston Avenue to West Cantey (water)
- West Lowden Street from Cleburne Road to 8th Avenue (water)
- Stanley Avenue from Cleburne Road to West Berry Street (water)
This capital improvement project is in Council District 9. Construction will impact the University Place, Frisco Heights, Paschal, Ryan Place Improvement and Las Familias de Rosemont neighborhood associations. Ryan Place Park is also in the construction area.
Location
W. Cantey Street at Stanley Avenue, Fort Worth 76110 View Map
32.7112116,-97.3460168
W. Cantey Street at Stanley Avenue ,
Fort Worth 76110
W. Cantey Street at Stanley Avenue ,
Fort Worth 76110