Design and construction of new and reconstruction of existing sidewalks, curb ramps, driveways, signs, and associated items like concrete curb and gutter and small retaining walls within an approximate quarter mile radius of both of the Daggett and D. McRae Elementary School campuses.
This project is in District 5 & 9
Daggett Elementary, contractor is working on remaining construction is approximately 95% completed. Signs and Pavement Markings will be installed in later December to early January.
D McRae Elementary, contractor is working on remaining construction is approximately 80% completed and working on Vaughn. Signs and Pavement Markings will be installed in later December to early January.
Historical Resources Survey Report Part 1 of 5(PDF, 527KB)
Historical Resources Survey Report Part 2 of 5(PDF, 6MB)
Historical Resources Survey Report Part 3 of 5(PDF, 5MB)
Historical Resources Survey Report Part 4 of 5(PDF, 6MB)
Historical Resources Survey Report Part 5 of 5(PDF, 2MB)
Project Scope Map - Daggett Elementary(PDF, 1MB)
Project Scope Map - D. McRae Elementary(PDF, 1MB)
958 Page Avenue, Fort Worth 76110 View Map
958 Page Avenue , Fort Worth 76110
Construction
February 2023
102403