Westcliff Drainage Improvements

  • Project typeDrainage Improvements
  • Project value$14,200,000
Drainage Improvements

This is a multi-phase project to reduce flooding in the Westcliff and South Hills neighborhoods. Part of the project involves installing new larger pipes and strategically relocating other pipes that carry heavy rain water away from residents and streets.

Council Districts: 3 and 9

 

January 2024 Project Status

Trail Lake Dr. has been paved and is open for traffic. Please use caution when driving in this area as other construction crews and equipment will be operating nearby and crossing Trail Lake Dr.

 

Project news

  • September 11, 2023 

    New streets identified for work as part of the on-going water, sewer, and storm drain construction in the Westcliff Neighborhood. 

     

 

Location

4300 clay ave, Fort Worth 76109  View Map

Google Map