Cromwell Marine Creek Road Widening

  • Project typeStreet & Transportation Improvements
  • Project value$37,240,000
Street & Transportation Improvements

Cromwell Marine Creek Road will be widened to a four-lane divided road. 

The project scope includes:

  • Right-of-way acquisition
  • Drainage improvements
  • Pedestrian lanes
  • Street lights
  • New bridge over Marine Creek
  • Modifications to the Marine Creek Pkwy. roundabout in coordination with the Texas Department of Transportation. 
  • Signalized intersections at Bob Hanger/Huffines Boulevard, Bowman Roberts Road, and Crystal Lake Drive

 

This project is in Council Districts 2 and 7.

 

February 2024 Project Update

A pre-construction public open house is set for Monday, February 26, 2024. The TPW project team will be on hand at the NWPD and District 7 open house to show plans and discuss the project. Monday, Feb. 26, 6:00 p.m. at 1600 Mustang Rock Road, Fort Worth, 76179

  • A Sundt Construction project trailer has been installed west of the Sokol Gymnasium.

    In addition, Sundt Construction will start removing trees between Boat Club Road and Huffines Boulevard.

Project meetings

  • There are no upcoming meetings at this time.

Project news

  • July 2023 Look Ahead
    1. The contractor and TPW will begin the process of relocating the franchise utilities. 
    2. The project manager and team will finalize Construction plans.
    3. The right of way acquisition will be finalized. 

Location

5900 Cromwell Marine Creek Road, Fort Worth 76179  View Map

Google Map