The Fort Worth City Cable Channel (Charter/Spectrum channel 190) will be offline for a few weeks starting March 11 while facilities connections are being rerouted. You can watch City meetings on the City’s LiveStreams or on our YouTube Channel.
PROJECT COMPLETE
Harmon Road has been rebuilt as a four-lane road from Golden Triangle Boulevard to US287. Roundabouts will be built at Golden Triangle Boulevard, Heritage Trace Parkway and Presidio Vista Drive.
Council Districts: 4, 7 and 10.
For additional information and maps, click here.
As of July 2023, the project is complete. The remaining task is for the City to conduct inspections for the acceptance of the project.
9600 Harmon Road, Fort Worth 76131 View Map
9600 Harmon Road , Fort Worth 76131
harmon-golden-triangle-closure-06-2022.pdf
COMPLETE
March 2023
100459