Park Vista Boulevard Improvements

  • Project typeStreet & Transportation Improvements
  • Project value$9,225,000
Street & Transportation Improvements

PHASE 1 - COMPLETE

Improvements to the Park Vista Boulevard and Keller Haslet Road intersection were made to improve traffic flow. A new traffic signal and left turn lanes along Keller Haslet Road are complete.

PHASE 2

The project will expand the current two lanes to a four-lane divided road with a median. The median will be positioned from Keller Haslet to Timberland Boulevard. Additional improvements include drainage, streetlights and bigger sidewalks.   

March 2024 Project Update

PHASE 2

  • The design plans are 100% complete.
  • Advertisement for construction bids has begun
  • Construction is planned to begin in summer of 2024.

 

This project is in Council District 10.

Project meetings

  • There are no upcoming meetings at this time.

Project news

  • There is no project news available at this time.

Location

4400 Keller Haslet Road, Fort Worth 76244  View Map

Google Map