The existing storm drain pipe at Thomas Place and Calmont Avenue is deteriorating and crosses residential lots. It will be relocated to within the City right of way and the existing pipe will be taken out of service.
Design is on-going and expected to be completed in March. Subsurface utility engineering will be taking place in the project limits in the next 30 days and 90% design submittal is expected. Bid documents are being prepared in preparation for construction advertisement.
Last update: March 2023
2700 Thomas Place, Fort Worth 76107 View Map
2700 Thomas Place , Fort Worth 76107
Design
June 2024
103057