Installation of a three-lane undivided concrete pavement section. Improvements to Keller Hicks and Katy intersection include:
Installation of a three-lane undivided concrete pavement section from Park Vista to Lauren Way. Improvements include:
This project is in Council District 10.
Project is at 60% Design.
Right of Way Acquisition is Complete.
Utility Relocation has begun and will continue through 2024.
Road Construction to begin when Phase 1 is complete and Phase 2 Utility Relocation is complete in 2025.
Meeting Slides:
Keller-Hicks-and-Park-Vista-60-Public-Meeting-3.pdf(PDF, 990KB)
View the public meeting:
Recording June 14 meeting
100 Keller Hicks Road, Fort Worth 76244 View Map
100 Keller Hicks Road , Fort Worth 76244
keller-hicks1.png
Phase 1 - Construction
Phase 2 - Design phase
Spring 2025
100146