This large City project is comprehensive and involves major improvements along Trinity Boulevard.
Phase 1 - from Loop 820 to Salado Trail.
This section of roadway will be reconstructed as a four-lane, divided concrete arterial. This project includes a landscaped median, multi-use trails on each side of the roadway and drainage system improvements.
A roundabout will be constructed at the entrance to the Trinity Lakes Development and a traffic signal will be reconstructed at the Salado Trail intersection. After project completion, Trinity Boulevard will no longer be in a floodplain.
Phase 2 - from Salado Trail to Thames Trail.
A four-lane, divided concrete arterial is planned for this section of Trinity Boulevard. A landscaped median, multi-use trails on each side of the road, drainage improvements and water and sewer lines will be constructed.
This project is in Council District 5.
Phase 2: The contractor has been selected and construction would start late summer 2024.
Construction Phasing Map(PDF, 1MB)
8400 Trinity Boulevard, Fort Worth 76053 View Map
8400 Trinity Boulevard , Fort Worth 76053
Phase 1: Construction
Phase 2: Design
Phase 1: October 2024
Phase 2: August 2027
Phase 1
Phase 2
Phase 1: 102101
Phase 2: 103280