This is a multi-phase project to reduce flooding in the Westcliff and South Hills neighborhoods. Part of the project involves installing new larger pipes and strategically relocating other pipes that carry heavy rain water away from residents and streets.
Council Districts 3 and 9
Storm drain outfall construction and sewer construction on Anita Ave is completed.
In the coming weeks, the following work will be underway:
.
September 11, 2023
New streets identified for work as part of the on-going water, sewer, and storm drain construction in the Westcliff Neighborhood.
4300 clay ave, Fort Worth 76109 View Map
4300 clay ave , Fort Worth 76109
Phase 1: Construction
Phase 2: Complete
Summer 2025
Stormwater Capital Project Bonds Funds
C01669