The 42-inch diameter Westside III Water Transmission Main will be constructed from the Westside Water Treatment Plant on Old Weatherford Road, south to a water ground storage tank site just south of I-20.
Part 1 will be constructed from the Westside Water Treatment Plant on Old Weatherford Road, south to Camp Bowie Boulevard or I-30. The exact alignment is being finalized. The 42-inch main will be part of the connection to the Westside II ground storage tank and the Westside IV and Westside V pump stations.
Part 2 will be constructed from Camp Bowie Boulevard or I-30 to just south of I- 20. The exact alignment is being finalized. The 42-inch main will be part of the connection to the Westside II ground storage tank and the Westside IV and Westside V pump stations.
The water ground storage tank site is located west of Markum Ranch Road, east and north of Aledo Road/FM 1024.
The water main will connect to the Westside II 24-inch water main. The two mains will connect to the Westside II ground storage tank and the Westside IV and Westside V pump stations.
The 42-inch diameter main is in Council District 3 and Fort Worth’s extraterritorial jurisdiction.
Other projects connected to the Westside III 42-inch Water Transmission Main project include:
12301 Camp Bowie Blvd., Fort Worth 76008 View Map
12301 Camp Bowie Blvd. , Fort Worth 76008
Design
Part 1: March 2024
Part 2: April 2025