This project includes relocating all left turn lanes at this intersection and constructing a dedicated northbound right turn lane with an island.
Additionally, the following are planned to improve this location:
This project is in Council District 6.
The project managers met with Transportation Management in November 2023 and it was determined that a lighting upgrade should be added to the design of the project. That will push the final design plans - at 90% - to come in around May 2024.
An anticipated bid for construction could then be in the fall of 2024.
8601 S Hulen St, Fort Worth 76132 View Map
8601 S Hulen St , Fort Worth 76132
Design
December 2025
103312