Keller Hicks Road Improvements

  • Project typeStreet & Transportation Improvements
  • Project value$23,941,453
Street & Transportation Improvements
  • Project 100146 - Keller Hicks Phase 1 - Lauren Way to US 377  

Installation of a three-lane undivided concrete pavement section. Improvements to Keller Hicks and Katy intersection include:

  1. Left turn lanes
  2. Traffic signal
  3. Improved railroad crossing for cars and pedestrians 
  • Project 103276 (Phase 2) - Keller Hicks Phase 2 - Park Vista Blvd to Lauren Way

 Installation of a three-lane undivided concrete pavement section from Park Vista to Lauren Way.  Improvements include:

  1. Street lights
  2. 10' sidewalks  
  3. Traffic signal at Woodland Springs
  4. Storm water drainage

 

This project is in Council District 10.

 

September 2025 Project Update

Phase 1: Project is complete

Phase 2: 

  • Project is under construction.  The contractor will start working South Side waterline.  This will require one lane to be closed at times.
  • Road to be closed between Park Vista and Gloriosa starting August 5, 2025 to October 3, 2025 for culvert construction. 
  • Expect road closures and one way traffic through the fall of 2026.
  • In mid-September, the Contractor will complete the culvert near Park Vista and begin construction on the culvert near Lauren Way.
Please see attached for future traffic control with culvert construction near Lauren Way. This closure will be in effect from mid-September through the End of November.

Traffic Control Plan(PDF, 4MB)