South Cravens Rd Drainage Project

  • Project typeDrainage Improvements
  • Project value$5,600,000
Drainage Improvements

Hazardous Road Overtopping Mitigation (HROM) improvements are planned to mitigate storm water from flowing over South Cravens Road.

The portion of the road from Oakdale Drive to Baylor Street will be raised and widened.

Several upgrades include:

• Storm drainage improvements to mitigate floodwater from overtopping the roadway

• Raise and widen the road over the new culverts

• New sidewalks and guardrails installed

• Curbs added along the road 

 

This project is in Council District 5.

 

July 2025 Project Status

  • Easement acquisitions are complete.

  • Prior to construction, a public meeting will be held in late fall or winter of 2025.  

     

Project meetings

Project news

  • Easement acquisitions are complete.
  • Preparation of 100% plans and specification complete in August 2024. 
  • Final Plans complete in September 2024. 
  • Bid and Award:  November/December 2024.
  • Mayor & Council Contract Approval:  January to April 2025.
  • Construction Start: April 2025.
  • Construction Complete:  March 2026. 
  • Construction Costs:  Approximately $3.3 M

 

 

Location

4120 S. Cravens Road, Fort Worth 76119  View Map