This large City project is comprehensive and involves major improvements along Trinity Boulevard.
Phase 1 - from Loop 820 to Salado Trail.
This section of roadway will be reconstructed as a four-lane, divided concrete arterial. This project includes a landscaped median, multi-use trails on each side of the roadway and drainage system improvements.
A roundabout will be constructed at the entrance to the Trinity Lakes Development and a traffic signal will be reconstructed at the Salado Trail intersection. After project completion, Trinity Boulevard will no longer be in a floodplain.
Phase 2 - from Salado Trail to Thames Trail.
A four-lane, divided concrete arterial is planned for this section of Trinity Boulevard. A landscaped median, multi-use trails on each side of the road, drainage improvements and water and sewer lines will be constructed.
This project is in Council District 5.
Phase 1:
Phase 2:
The contractor has completed the north half of the pavement, and the project is now open to two-way traffic on the North Side. Expect the existing traffic control to remain in place through June 2026 as the contractor works on the sidewalk and illumination on the south side of the road. Sequin will be able to open to traffic again after concrete tests are accepted.
Expect to see work on sidewalks, illumination, traffic signal, irrigation, and landscaping through June 2026.
Additional Resources
8400 Trinity Boulevard, Fort Worth 76053 View Map
8400 Trinity Boulevard , Fort Worth 76053
Phase 1: Construction
Phase 2: Construction
Phase 1: Spring 2026
Phase 2: August 2026
Phase 1
Phase 2
Phase 1: 102101
Phase 2: 103280