Riverside Street Improvements
- Project typeStreet & Transportation Improvements
This street improvement project is located in the Riverside area.
The streets scheduled for rehabilitation with water, sewer, storm, and paving improvements include:
. Clarence St from Airport Fwy to Wheeler St
• Blandin St from Bird St to McLemore Ave
• Dell St from Blandin St to N Chandler Dr
• Grapewood St from N Chandler Dr to N Riverside Dr
• Plumwood St from N Chandler Dr to N Riverside Dr
• Oak Knoll Dr from wheeler St to airport freeway
• Wayne St from Wheeler St to Airport Freeway
• Shadow Ln from Wheeler St to Airport Freeway
• Fox Dr from Shadow Ln to Kings Highway
• Airport Freeway from Shadow to Oak Knoll Dr
This project is located in Council District 11.
March 2026 Project Status
What's Happening Now
-
The new water and sewer lines on Dell St. and Blandin St. have been installed.
-
Work on private property has been completed. Crews have put down temporary pavement until the permanent pavement is installed.
-
The new sewer lines on Plumwood St and Grapewood have been installed. Work on the water lines is in progress and will be completed by mid-March.
-
Work on the water and sewer lines in Fox Dr and Shadow Ln is in progress
What's Coming Next
More Information:
If you’d like more information about the project, you can find details and frequently asked questions in the October 2025 Presentation.
October 2025 Presentation(PDF, 9MB)
Watch October 8, 2025 Meeting
City Inspector is Adrian Aranda
682-329-6655
Adrian.Aranda@fortworthtexas.gov
Project news
- There is no project news available at this time.