Wedgwood and Candleridge Area Water Main and Sewer Main Replacement

  • Project typeWater and Wastewater Improvements
Water & Sanitary Sewer Imrpovements

 Water and sewer mains will be removed and replaced in an area that is bound by: 

  • Wrigley Way and Wheelock Drive to the north
  • Altamesa Boulevard to the south
  • South Hulen to the east, and
  • Trail Lake Drive to the west.

 

The water mains are cast iron, asbestos cement, PVC, and ductal iron. Water lines and sewer mains will be removed and replaced.

 

Water and Sewer Main Replacements

Whistler Drive from Trail Lake Drive to South Hulen Street

  • Water line is asbestos cement pipe and cast iron

Winesanker Way from Winifred Drive to Alta Mesa Boulevard

  • Water line is PVC and asbestos cement pipe

Winifred Drive from Winesanker to Alta Mesa Boulevard

  • Water line is in cast iron

Whitman Avenue from Whistler Drive to Alta Mesa Boulevard

  • Water line is asbestos cement pipe and cast iron

Lancelot Court from Winesanker Way to Winchester Court

  • Water line is asbestos cement pipe

Winchester Court from Winesanker Way to Alta Mesa Boulevard

  • Water line is asbestos cement pipe and ductal iron pipe

Wilton Court from Winesanker Way to Alta Mesa Boulevard

  • Water line is asbestos cement pipe

 

Water Main Replacements Only

Whistler Court from Whistler Drive to the cul-de-sac

  • Water line is cast iron

Alta Mesa Boulevard from Whitman Avenue, southwest to 805 feet

  • Water line is cast iron

Willis Place from Winesanker Way to Alta Mesa Boulevard

  • Water line is ductal iron

 

This Fort Worth Water capital improvement project is in Council District 9 and borders Fort Worth Council District 6. This project is mainly residential. The project will impact the Candleridge neighborhood association, the Wedgwood Square neighborhood association and Wedgwood South neighborhood association. 

 

Project Meeting

 

 

Project News

Location

Winesanker Way at Lancelot Court, Fort Worth 76133  View Map