Safe Routes to School - C.C. Moss & M.L. Phillips

  • Project typeStreet & Transportation Improvements
  • Project value$3,400,000
Street & Transportation Improvements

Design and construction of new and reconstruction of existing sidewalks, curb ramps, driveways, signs, and associated items like concrete curb and gutter and small retaining walls within an approximate quarter mile radius of both of the C. C. Moss and M. L. Phillips Elementary School campuses.

This project is in Council District 3 & 5

 

January 2023 Project Update

Project is nearing completion with remaining signs and pavement markings being placed this month. Some activity will remain in the area until all work in completed and final inspection conducted. Project overall is 99% completed. 

 

Project meetings

  • There are no upcoming meetings at this time.

Project news

  • A Notice and Opportunity for Comment process has begun for this project and ends on Saturday June 26th. For more information, see the link on this page below.

     

 

 