The channel improvements for Brandon Lane Channel and 6th Avenue Channel include protecting infrastructure, installing retaining walls, grading channels, and installing erosion protection to ensure the channels effectively convey stormwater runoff to mitigate flood and erosion risk.
The Brandon Lane Channel construction limits are between Brandon Lane & Socorro Road (east/west) and approximately 325’ north of Monmouth Drive & Bangor Drive (north/south). This is located in Council District 3. The 6th Avenue Channel construction limits are between Truelson Drive & 6thAvenue (east/west) and California Pkwy Sout & Edgecliff Road (north/south) . This is located in Council District 6.
This project is located in Council Districts 3 & 6.
June 2023 - Bid Advertisement
September 2023 - Mayor and Council Contract Approval
March 2025 – Community Meeting
March 2025 – Pre-construction meeting
April 2025 – Begin Construction
February 2026 – Anticipated End of Construction
Watch the City's March 10, 2025 Project Meeting.
Watch Meeting
Coming soon in march 2025
3400 Brandon Lane, Fort Worth 76116 View Map
3400 Brandon Lane , Fort Worth 76116
Pre-construction
Winter 2025
103066