Cantrell Sansom Road

  • Project typeStreet & Transportation Improvements
  • Project value$7,790,935
Street & Transportation Improvements

Cantrell Sansom Road will be widened between Mark IV Parkway and the future IH-35W southbound frontage road.

Widening will make way for the addition of two westbound and two eastbound lanes.

 

This project is located in Council District 2.

 

February 2026 Project Update

Thank you to those in the community who attended our February 5, 2026 meeting. 

See the presentation and upcoming construction timeline below.

Construction Schedule Presentation(PDF, 3MB)

  • Contractor to begin construction on March 9 and last 10-12 months.  Contractor will begin Phase 1 and work on Cantrell Sansom from Old Denton Road to IH35W Southbound Frontage Road.  This Phase will last from March to June 2026.
  • Contractor to close Old Denton Road at Cantrell Sansom Road.  Detours will be set up to use Mark IV Parkway and IH35W Southbound Frontage Road.  Please utilize all detours and avoid the construction zone.  Contractor expects to be opening pavement in all directions by September 2026.

Project meetings

  • There are no upcoming meetings at this time.

Project news

  • There is no project news available at this time.