Culvert improvements are proposed for Comanche Trail between Malaga Drive and Marina Drive to address existing hazards from flood waters overtopping this location. In conjunction with the culvert improvements, the road will be widened and elevated to reduce the probability of flood waters flooding the roadway during high intensity rainfall events.
August 2023 Update
The construction schedule for Comanche Trail Hazardous Road Overtopping Mitigation project has been extended due to structural deficiencies discovered in the culvert footings during the construction inspection process, which require removal and replacement for safety reasons.
The good news is that construction begins again this month. Here are the approximate updated milestones, weather permitting.
The project is located in District 7.
7300 Comanche Trail, Fort Worth 761135 View Map
7300 Comanche Trail , Fort Worth 761135
Construction
January 2024