The project involves improvements on two major streets in downtown Fort Worth.
Damaged concrete panels will be replaced on the following:
E. Belknap St from Pecan St to Nichols St
E Weatherford St from Pecan St to Nichol St
These locations involve replacing all damaged sidewalks and driveways.
This project is located in Council District 9.
E. Weatherford St and E. Belknap St construction was completed on May 29. Both streets are open to traffic.
100 Harding St, Fort Worth 76102 View Map
100 Harding St , Fort Worth 76102
COMPLETE
May 2026