Exposition Way Slope Project

  • Project typeStreet & Transportation Improvements
  • Project value$1,694,000
Street & Transportation Improvements

The Transportation and Public Works Department will be using PayGo funding to improve Exposition Way from Sam Bass Trail to Heritage Trace Parkway.

The project includes:

  • slope stabilization
  • concrete panel replacement
  • crack and joint sealing

Only damaged curb and gutter, sidewalks, and non-compliant curb ramps will be replaced.

 

This project is located in Council District 10.

November 2026 Project Status Update

  • The project team is in the process of bidding the contract for construction. 

Project meetings

  • There are no upcoming meetings at this time.

Project news

  • There is no project news available at this time.

 

Location

4932 Exposition Drive, Fort Worth 76244  View Map