Greater Como & Rosemont Area Improvements

  • Project typeStreet & Transportation Improvements
  • Project value$14,500,000.00
Street & Transportation Improvements

Plans are underway for street improvements to fourteen streets located in the Greater Como and Rosemont areas.

The following streets and easements will be repaved with upgrades to the water, sewer and storm water drainage:

  1. Carver Dr, from Prevost St to Hervie St

  2. Fernander Dr, from Prevost St to Hervie St

  3. 8th Ave, from W Dickson St to W Pafford St

  4. Frazier Ave, from Cleburne Rd to W Biddison St

  5. Frazier Ave (S), from W Bolt St to Flint St

  6. Townsend Dr, from W Drew St to Flint St

  7. Wayside Ave, from W Drew St to W Bolt St

  8. Drew St,  from Wayside Ave. to Frazier Ave.

  9. Bolt St,  from McCart Ave. to East Rail Road

  10. Prevost St,  from 163 feet north of Carver St to Vickery Blvd

  11. Townsend Dr,  from Flint St. to Pafford St.

  12. Carver Dr, from Prevost St to Merrick St

  13. Wayside Ave, from Biddison St to Butler St

  14. Wayside Ave, from Dickson St to Waggoman St

  15. Easement between Frazier Ave. & Townsend Dr, from Bolt St. to Flint St.

  16. Easement between Townsend Dr. & Railroad on East, from Bolt St. to Flint St.

 

This project spans City Council Districts 6, 9 and 11.  

 

December 2025 Project Status 

  • The concrete paving is complete on Frazier Ave. (W Biddison St. to Cleburne Rd.) and on 8th Ave. (Dickson St. to W Pafford St.)

  • Street pavement removal and subgrade prep is complete on Townsend Dr.

Coming up crews will,

  • begin street paving on Townsend north bound lane (Flint St. to Drew St.)

  • begin concrete street paving on Frazier Avenue north bound lane (Flint St. to Bolt St.)

     

     