This project includes improvements at the Marine Creek Parkway and IH-820 intersection to improve the intersection capacity and enhance operational flexibility. The project has two (2) phases.
Phase one (1) includes the installation of an eastbound U-turn lane and construction of approximately nine hundred (900) linear feet of ten (10) foot hike & bike trails on the east side of Marine Creek to connect to a future Park and Recreation project. This phase is entirely funded with the City’s funds.
Phase two (2) includes installing northbound and southbound displaced left-turn lanes into the existing diamond interchange. This phase is funded with the City’s funds and Federal funds.
This project is located in Council District 2
4700 Marine Creek Parkway, Fort Worth 76179 View Map
4700 Marine Creek Parkway , Fort Worth 76179
101585-1.jpg
101585-2.jpg
101585-3-marine-creek.png
101585-4-marine-creek.png
cpn101585-p01.png
cpn101585-p02.png
cpn101585-p03.png
cpn101585-p04.png
Construction
Phase 1: December 2023
Phase 2: December 2025
101585