A 24-inch in diameter water transmission main will be installed in northwest Fort Worth in the Northpointe area.
The main will start at Park Drive - just east of Boat Club Road - and extend northeasterly along the proposed extension of Heritage Trace Boulevard. Construction ends just north of the intersection of Assembly Road and North Water Tower Road, on Heritage Trace Boulevard.
Construction will likely impact traffic on Park Drive.
This project is in Fort Worth Council District 7 and impacts the Northwest Fort Worth Neighborhood Alliance.
Heritage Trace Boulevard at Little Tree Lane, Fort Worth 76179 View Map
Heritage Trace Boulevard at Little Tree Lane , Fort Worth 76179
Construction
December 2022
103505