This project will provide a new transit bus center near Envision Center and the Stop Six neighborhood in southeast Fort Worth.
This project is located in Council District 5.
June 2023 Update:
Contractor is continuing work on Burton Avenue and Crouch Street installing utilities. Utility work will continue through the end of June 2023, after which paving will begin starting in July 2023.
Utility work on Chickasaw is expected to commence in July 2023.
4651 Ramey Ave, Fort Worth 76105 View Map
4651 Ramey Ave , Fort Worth 76105
Early Design planning
Winter 2026
Caville/Stop Six Roadway Redevelopment
104804