Greenfield Acres Drainage Improvements

  • Project typeDrainage Improvements
  • Project value$7,200,000
Drainage Improvements

Phase 3 of the Greenfield Acres Drainage project is complete. 

The final Phase 4 of this project will involve the construction of storm drain lines, some sanitary sewer lines, and street repaving on Greenfield Road (east of Cindy Lane), Tee Head Drive, North Hill Road (Lea Crest Lane to Tee Head Drive) and ditch re-grading along Cindy Lane.  Construction is planned to start in April 2023 and will last 1-year.

 

March 2023 Update

  • The contract for this phase was awarded by council on February 14 to Fort Worth Civil Constructors, LLC and contracts are currently being executed.
  • A community meeting will be scheduled in April 2023.

This project is in Council District 2

 