Mistletoe & Alamo Heights Street Improvements

  • Project typeStreet & Transportation Improvements
  • Project value$5,400,000
Street & Transportation Improvements

The project provides for the design of water, sewer, and paving improvements on twelve neighborhood streets:

  • Buck Ave, from W Rosedale St S to Mistletoe Ave.
  • Chambers Ave, from Alamo Ave to W Vickery Blvd.
  • Gordon Ave, from McPherson Ave to W Lowden St.
  • Lipscomb St, from Page St to W Capps St.
  • Livingston Ave, from W Lowden St to W Bowie St.
  • Lisbon, from Chambers to Landers St.
  • Rutledge St, from Vickery Blvd  to Landers St.
  • Landers St, from Locke Ave.  to Lovell Ave.
  • Mistletoe Drive, from Alley between Mistletoe Avenue and Edwin Street to Rosedale St.
  • Harrison Avenue, from Buck Avenue to Mistletoe Drive
  • Mistletoe Boulevard, from Buck Avenue to Mistletoe Drive
  • Alley between Alamo Ave. & Valentine St. from 370 ft south of Chambers Ave. to West Freeway
  • Alley between Lisbon St. & Vickery Blvd, from Bedford St, to 144 ft. north of Chambers Ave.

 

This project is located in Council Districts 3 & 9.

 

February 2026 Project Update

Construction schedule(PDF, 356KB)

What’s Happening Now

  • The new water lines on Buck Ave, Harrison Ave, Mistletoe Dr, Mistletoe Blvd and Lipscomb St have been installed. Crews have put down temporary pavement until the permanent pavement is installed.
  • Work is paused on the driveways, sidewalks, and curbs along Buck. This part of the work will resume in the spring.
  • Work is moving forward on the water line in Gordon St and should be completed by early March.
  • The paving work on Lipscomb St is in progress.

What’s Coming Next

  • Permanent paving on Buck Ave, Harrison Ave, Mistletoe Dr and Mistletoe Blvd will begin in the spring.
  • Work on the water line on Livingston St will begin in March.

More Information:

If you’d like more information about the project, you can find details and frequently asked questions in the June 2025 Presentation.

 

Contact Details: 

Project Manager: Justina Samaan 

817-392-5536

Justina.Samaan@fortworthtexas.gov

 

Inspector: Hector Montoya

682-215-9539

Hector.Montoya@fortworthtexas.gov

 

Project meetings

  • There are no meetings scheduled at this time

Project news

Not at this time

 

 