Riverside Street Improvements

  • Project typeStreet & Transportation Improvements
Street & Transportation Improvements

This street improvement project is located in the Riverside area. 

The streets scheduled for rehabilitation with water, sewer, storm, and paving improvements include:

. Clarence St from Airport Fwy to Wheeler St

• Blandin St from Bird St to McLemore Ave

• Dell St from Blandin St to N Chandler Dr

• Grapewood St from N Chandler Dr to N Riverside Dr

• Plumwood St from N Chandler Dr to N Riverside Dr

• Oak Knoll Dr from wheeler St to airport freeway

• Wayne St from Wheeler St to Airport Freeway

• Shadow Ln from Wheeler St to Airport Freeway

• Fox Dr from Shadow Ln  to Kings Highway 

• Airport Freeway from Shadow to Oak Knoll Dr

 

This project is located in Council District 11.

June 2026 Project Status

What's Happening Now

  • New water lines on Airport Fwy and Wayne St have been installed. Clarance St water line is in progress.Crews have put down temporary pavement until the permanent pavement is installed.

  • The new sewer lines on Airport Fwy have been installed.

  • Pavement removal on Blandin St & Dell St has been completed.

What's Coming Next

  • Install new sewer line on Clarence St and Wayne St starting June 2026.

  • Permanent concrete pavement work on Blandin St & Dell St will begin June 2026.

  • Plumwood St & Grapewood St pavement removal will begin late June 2026.

     

More Information:

If you’d like more information about the project, you can find details and frequently asked questions in the October 2025 Presentation.

October 2025 Presentation(PDF, 9MB)

 Watch October 8, 2025 Meeting 

City Inspector is Adrian Aranda

682-329-6655

Adrian.Aranda@fortworthtexas.gov

 

Project meetings

Project news

  • There is no project news available at this time.