South Cravens Rd Drainage Project

  • Project typeDrainage Improvements
  • Project value$5,600,000
Drainage Improvements

Hazardous Road Overtopping Mitigation (HROM) improvements are planned to mitigate storm water from flowing over South Cravens Road.

The portion of the road from Oakdale Drive to Baylor Street will be raised and widened.

Several upgrades include:

• Storm drainage improvements to mitigate floodwater from overtopping the roadway

• Raise and widen the road over the new culverts

• New sidewalks and guardrails installed

• Curbs added along the road 

 

This project is in Council District 5.

 

February 2026 Project Status

  • Construction is underway.

 

Project meetings

Project news

  • Construction Start: January 2026
  • Construction Complete:  October 2026 
  • Construction Costs:  Approximately $5.1 M

 

 

Location

4120 S. Cravens Road, Fort Worth 76119  View Map