October 2, 2026 Update
The City does not set the work schedule. The information shared below is based on the latest schedule the City received from the contractor. Weather and other factors can cause delays.
Fully completed work completed
- North Bailey Avenue from Sherwood Drive to Lakewood Road
- Lindenwood Drive from White Settlement Road to Crestwood Terrace
- Eastwood Avenue between 400 and 420 Eastwood Avenue
- Easement from Rockwood Park Drive to Crestwood Drive
Road Repairs
This work has three phases. The first phase is the concrete flat work, which entails repairing the curbs, gutters and driveways damaged by the utility work. The second phase is pulverizing the existing road from curb to curb, stabilizing and compacting the pulverized base material. The third phase is overlaying the base with asphalt. Before the asphalt is overlayed, the base must pass compaction tests.
The contractor’s latest projected pavement reconstruction schedule is outlined below. Weather could delay the schedule.
Remaining work:
There is sewer work to be done in five areas and water main work remaining on three streets. The following is a breakdown of the remaining work by street along with the contractor’s projected schedule.
- Crestwood Drive between 408/409 Crestwood Drive and the dead end
- Sewer installation is complete.
- The concrete flatwork is complete.
- The pulverization and asphalt overlay is scheduled to start Oct. 19.
- Crestwood Drive from White Settlement Road to Crestwood Terrace
- Install fabric below sewer line on Crestwood Drive between White Settlement Road and Crestwood Terrace starting Oct. 5.
- Water main pressure testing is in progress. Once the main passes pressure testing, bacteriological testing will occur.
- Once the water main passes all testing, customer tie-ins and service transfers to the new water main will be performed. No date is available at this time.
- A temporary asphalt repair will follow.
- The concrete flatwork is projected to start Nov. 6 but is dependent on completion of steps listed above.
- The road pulverization and asphalt overlay is projected to start Jan. 5, 2027.
- North Bailey Avenue from Crestwood Terrace to Sherwood Drive
- Corrections needed to the sewer line grade issue on Sherwood Avenue at North Bailey Avenue are planned to begin Oct. 13.
- Repairs to curbs, gutters and driveways are in progress.
- The pulverization and asphalt overlay is scheduled to begin Nov. 2.
- Crestwood Terrace
- The concrete flatwork is scheduled to begin Oct. 13
- Road pulverization and asphalt overlay is projected to start on Dec. 18.
- Cresthaven Terrace from North Bailey Avenue to Rockwood Park Drive
- The remaining sewer work includes installing a new sewer cleanout, lining an existing sewer pipe, and plugging, grouting and abandoning an existing six-inch concrete sewer line. The contractor is waiting on confirmed schedule dates from the subcontractor who will perform this work.
- The road pulverization and asphalt overlay is projected to start Nov. 30
- Ridgewood Road from Crestwood Drive to Cresthaven Terrace
- Complete remaining sewer work and service connections starting on Oct. 5.
- Install water main starting on Oct. 5.
- Water main pressure and bacteriological testing are projected to start on Nov. 11
- Begin transferring customers to new water line on Nov. 24, followed by temporary asphalt repair.
- Begin concrete flatwork on Dec. 3
- Begin road pulverization and overlay on Jan. 27
- Rockwood Park Drive
- Replacing the existing manhole on Rock Creek Park Drive north of Cresthaven Terrace is pending because of an issue with proximity to the raw water line.
What the City is doing
- Inspecting remaining construction work to ensure compliance with engineering plans and specifications.
What You can Do
- Do not park cars on the street to facilitate water line installation and road repairs. The contractor will leave door tags with information on these dates. Having cars parked on streets can delay completing the work.
- Homes on temporary water lines should limit outdoor watering to between 10 p.m. and 4 a.m. Multiple homes running irrigation at the same time will impact pressure.